This site uses cookies to improve your experience and optimize your experience. By continuing to use this site, you agree to our use of cookies on this site. Read more
Back

Details:

  • Client:

    Gemeindeverwaltung Klettgau

  • Period:

    06/2022 - 06/2023

  • Place:

    Klettgau Self-government, Baden-Wurttemberg, Germany

Description:

Construction of full optical network: trenching, horizontal drilling, pipe laying, supply and installation of switchboards / access points (POPs), cable pulling and blowing, optics assembly and measurement, power supply, electrical equipment and passive optical equipment assembly, installation and assembly of optical network distribution cabinets, shafts, construction of building connections.

Project volumes:

  • Lot No. 1: construction of 25 km optical network route and connections for about 600 buildings, the project must be implemented before 04/2023;
  • Lot No. 2: construction of 22 km optical network route and connections for about 230 buildings, the project must be implemented before 06/2023.

Citrus Solutions GmbH will perform all works as a general contractor.