Details:

  • Client:

    General partnership BERERIX

  • Period:

    11/2020 - 06/2023

  • Place:

    Riga

Description:

Design, construction and installation of external low-voltage power networks for Rail Baltica project sections: Riga Railway Bridge, Riga Railway Embankment, new structure of Riga Central Passenger Station Complex. In some sections, the network is relocated, but mostly it is completely reconstructed.

The low-voltage network to be constructed is intended for the following electronic communications operators: the Latvian State Radio and Television Centre (LVRTC), Tet, Telia Latvia, Latvijas dzelzceļš, Baltcom, RETN Baltic, LMT, Balticom, Netvision.

The total length of the cables envisaged in the contract is about 75 km.